Equipment
EWA approved renewable energy systems' equipment & components, such as photovoltaic (PV) panels, inverters, external interface protection units and direct current (DC) cables, must all meet the highest international safety and quality standards to ensure that the installed renewable energy systems on customers' premises are innovative, safe and efficient.
Service Information
Application Process
-
Submit application and required documents at EWA’s Head Office in Diplomatic Area.
-
Receive submission acknowledgment email; resubmission may be required if any documents are missing or need revision.
-
Receive approval letter by email.
Documents Required
- Renewable Equipment Licensing
- Technical Drawings
- Technical Datasheets and catalogues of the requested products
- Type Test Reports and Certificates from an independent accredited testing Laboratory
- Laboratory Scope of accreditation in accordance with ISO/IEC 17025:2017
- ISO 9001:2015 Quality Management System Certificate of the manufacturer
- Additional technical documents may be requested as per list of submittals in service request form
Service Fees
- No Fees
Service Duration
- 5 Working Days
Service Steps
-
Submit ApplicationSubmit your application for Renewable Energy Equipment Licensing, along with all required documents, at the EWA's Head Office in Diplomatic Area.
-
Application ReviewOur team will review your submitted equipment documents to ensure compliance with EWA’s regulations and standards. If any requirements are missing or need revision, you will be notified to resubmit the necessary information.
-
Approval ReleaseOnce your application is approved, you'll receive an official approval letter by email.
-
Your Service is Complete
Service Tip
Before applying, ensure that all requested equipment is certified in accordance with valid GSO, IEC, EN, or BS standards.