Net-Metering/ Net-Billing
If you want to benefit from solar energy by connecting your premises to the electricity grid and having excess energy credited to your bill to reduce costs and support renewable energy, this service is for you. It is provided under an agreement with a contractor and licensed engineering office.
Service Information
Application Process
-
Before submitting the application, appoint an EWA-approved contractor and engineering office to submit the application and required documents through the Benayat channel.
-
Choose an approved engineering office to submit the required documents through the Benayat platform.
-
Please select the appropriate "Level" of contractors and engineering offices according to the system capacity, as listed in the table below:
SolarPV System Capacity
Up to (20 kW)
Up to (100 kW)
Up to (1000 kW)
Above (1000 kW)
A, B, C, D A, B, C A, BAA, CA, C A, B+CA, B+C
Service Fees
- No Fees
Service Duration
- 8 Working Days
Service Steps
-
Assign Approved Contractor & Engineering OfficeAssign an EWA-approved contractor and engineering office. Your contractor will submit your request along with the required documents through Benayat.
-
Engineering Office ReviewYour engineering office will review the submitted request and approve it through the platform.
-
EWA Review & InspectionOnce approved by your engineering office, EWA will review your request and carry out a field inspection of your premises.
-
System ConnectionAfter EWA’s final approval, your system will be connected to the electricity grid.
-
Your Service is Complete